At Graphite Square we have finished constructing the massive basement with 80% of the ground floor slab now poured.
Blocks are loaded ready to construct the inner walls to the Basement meanwhile above ground Blocks B & C are almost at level 2 with Block A ground floor scheduled for pour in the next 7 days.