Church Road, Mitcham
Our Church Road Mitcham project will shortly be completing to provide 20no Apartments for Affordable Rent for Moat Homes.
The Apartments and communal areas are in the final decoration stages with floor finishes being fitted and Client snagging due imminently
Read more
Graphite Square, Lambeth
Our Flagship project at Graphite Square is progressing well
Demolition works are nearing Completion and works have commenced to install the piling mat for the Piling Commencement shortly
Our Phase 1 Site Set up is now in place and Operational and provides a base for our Site Management Team and our RLO
Read more
Foxley Lane, Purley
Works have now commenced on our Foxley Lane Purley project to provide 41no. Apartments for Moat Homes
Ground Beams, Drainage, Lift Pits and Pad foundations are now complete, works are now focused on installing the Ground floor Slab
Vertical Column starters now in place ready for the RC Frame construction
Formwork in place for the new RC Core walls and Lift shafts
Read more
Stirling Road, Acton
Level 5 slab now being Constructed
Level 6 slab now poured, Columns and Cores now being formed for 7th Floor level
Read more
Graphite Square, Lambeth
Demolition ongoing for the last phase
Prep for Pile Mat had started
Read more
Graphite Square, Lambeth
Demolition works are well underway at our new site
Read more
Graphite Square, Lambeth
Vision are delighted to announce successfully securing The Graphite Square landmark new build project which consists of 80,000 sq ft of Commercial space across the lower three floors of the development & 160 mixed-use Residential 1, 2 & 3 bedroom apartments. Vision are proud to be working on this project and with demolition of the existing buildings well underway, we are excited to progress onto to next stage of the development.
Read more
Roslin Road, Acton
Piling complete
Foundations 90% complete
Stub walls commenced
Below ground drainage commenced
63.8M Crane being erected imminently
Read more
Church Road, Mitcham
Kitchens are getting installed on 3rd and 2nd floors
Doors, arcs and skirting getting installed on the 1st floor. That’ll be 3rd, 2nd and 1st complete by the end of the week.
Boilers installation continuing throughout the 2nd floor.
Groundworks/landscaping/fencing to the rear patios started
Read more
Stirling Road, Acton
One of Vision Construct's new site has now officially started.
Groundworks contractor completed below ground drainage
Steel fixers have started to tile steel for the ground floor slab
Groundworks contractor excavating, forming steel reinforcement cages and pouring concrete, for pile caps and ground beams
Read more
Roslin Road, Acton
Groundworker commenced
Pile cropping underway
Pile integrity testing carried out to first set of piles
Read more
Roslin Road, Acton
One of Vision Construct's new site has now officially started.
Piling completed
Exploratory work in the footpath started
Read more
The Crane, Hayes
1st and 2nd fix ongoing to all floors
Installation of internal SVP’s and installation of fire collars
Roofing works on going and capping commencing
Installation of windows progressing
Boarding to bathrooms proceeding after installation of SVP’s and fire collars to progress 2nd fix M&E
Read more
Church Road, Mitcham
Fire stopping works to the penetrations have started
Closing up the walls will starting
Metal ceilings work continues
Lift installation work started
Exterior snagging to the top floor will be complete and ready for scaffold strike
Read more
Church Road, Mitcham
1st fix electric and plumbing will be completed by the end of the week
Lift installation starting next week
Roof coverings and outlets to be finished
Fire rating penetrations to start next week
Read more
York Road, Battersea
Met – Sec inner leaf to external façade – 100%
External doors and windows – 40%
External brickwork / cladding – 80%
Sub – Station Construction – 80%
Roof coverings – 20%
Internal metal stud walls & board one side – 90%
First fix M & E inc plant rooms – 60%
Read more
Church Road, Mitcham
3rd floor screed complete
1st Floor plumbing and electrical 1st fix now complete
Roof now 85% Complete
Read more
The Crane, Hayes
Internally - 1st fixing electrical, mechanical, sprinklers and flat duct
Externally - finishing parapet walls on the top roof in readiness for the roof coverings
The lower roof is complete and the carpenters are now putting the joists on the middle roof and installing the firrings.
Read more
The Crane, Hayes
Plying the upper roof
Lower roof is having the membrane installed
1st fixed metal on the ground, 1st and 2nd floor
Electricians have started 1st fix
Plumbers have started putting up soil stacks
Gas risers this week
Read more
Church Road, Mitcham
First fix electric cabling started to the ground floor and containment to the corridors/communal.
Metal studwork 70% complete throughout.
Roof timbers / furrings / OSB decking ongoing
Brickies building-up facework to the 3rd floor parapet.
Read more
Campbell Road, Croydon
Vision are pleased to announce that Campbell Road is now complete
Read more
Sunbury Street, Woolwich
Internal second fix carpentry
Second fix mechanical and electrical
Mist coat decorations
Tiling
Bathroom sanitary ware install
Incoming services
Mechanical plant install
Read more
Campbell Road, Croydon
Flats 3 & 4 tiling to disabled bathrooms complete
General snagging and final decorations to flats
Stair cores decorations
Read more
Hyde Vale, Greenwich
Unit 1-4 Garden rooms green roof’s installed.
Roof lights to unit 1-4.
Portland stone copings completed to units 1-4 rear elevation with green roof installed.
1ST Floor windows installed on front elevation with Portland stone to window reveals.
Read more