Block A: Façade SFS stud installations have progressed up to 8th floor. CP panel installations progressed up to 4th floor. Block B: Façade SFS stud installations have progressed up to 10th floor. CP panel installations progressed up to 4th floor. Block C: Façade SFS stud installations have progressed up to 10th floor. CP panel installations progressed up to 8th floor.