Architecture (42)

Graphite Square, Lambeth

Vision are delighted to announce successfully securing The Graphite Square landmark new build project which consists of 80,000 sq ft of Commercial space across the lower three floors of the development & 160 mixed-use Residential 1, 2 & 3 bedroom apartments. Vision are proud to be working on this project and with demolition of the existing buildings well underway, we are excited to progress onto to next stage of the development.
Read more
Roslin Road, Acton

Roslin Road, Acton

Piling complete Foundations 90% complete Stub walls commenced Below ground drainage commenced 63.8M Crane being erected imminently
Read more
Church Road, Mitcham

Church Road, Mitcham

Kitchens are getting installed on 3rd and 2nd floors Doors, arcs and skirting getting installed on the 1st floor. That’ll be 3rd, 2nd and 1st complete by the end of the week. Boilers installation continuing throughout the 2nd floor. Groundworks/landscaping/fencing to the rear patios started
Read more
Stirling Road, Acton

Stirling Road, Acton

One of Vision Construct's new site has now officially started. Groundworks contractor completed below ground drainage Steel fixers have started to tile steel for the ground floor slab Groundworks contractor excavating, forming steel reinforcement cages and pouring concrete, for pile caps and ground beams
Read more
Roslin Road, Acton

Roslin Road, Acton

One of Vision Construct's new site has now officially started. Piling completed Exploratory work in the footpath started
Read more
The Crane, Hayes

The Crane, Hayes

1st and 2nd fix ongoing to all floors Installation of internal SVP’s and installation of fire collars Roofing works on going and capping commencing Installation of windows progressing Boarding to bathrooms proceeding after installation of SVP’s and fire collars to progress 2nd fix M&E
Read more
Church Road, Mitcham

Church Road, Mitcham

Fire stopping works to the penetrations have started Closing up the walls will starting Metal ceilings work continues Lift installation work started Exterior snagging to the top floor will be complete and ready for scaffold strike
Read more
Church Road, Mitcham

Church Road, Mitcham

1st fix electric and plumbing will be completed by the end of the week Lift installation starting next week Roof coverings and outlets to be finished Fire rating penetrations to start next week
Read more
York Road, Battersea

York Road, Battersea

Met – Sec inner leaf to external façade – 100% External doors and windows – 40% External brickwork / cladding – 80% Sub – Station Construction – 80% Roof coverings – 20% Internal metal stud walls & board one side – 90% First fix M & E inc plant rooms – 60%
Read more
The Crane, Hayes

The Crane, Hayes

Internally - 1st fixing electrical, mechanical, sprinklers and flat duct Externally - finishing parapet walls on the top roof in readiness for the roof coverings The lower roof is complete and the carpenters are now putting the joists on the middle roof and installing the firrings.
Read more
The Crane, Hayes

The Crane, Hayes

Plying the upper roof Lower roof is having the membrane installed 1st fixed metal on the ground, 1st and 2nd floor Electricians have started 1st fix Plumbers have started putting up soil stacks Gas risers this week
Read more
Church Road, Mitcham

Church Road, Mitcham

First fix electric cabling started to the ground floor and containment to the corridors/communal. Metal studwork 70% complete throughout. Roof timbers / furrings / OSB decking ongoing Brickies building-up facework to the 3rd floor parapet.
Read more
Sunbury Street, Woolwich

Sunbury Street, Woolwich

Internal second fix carpentry Second fix mechanical and electrical Mist coat decorations Tiling Bathroom sanitary ware install Incoming services Mechanical plant install
Read more
Hyde Vale, Greenwich

Hyde Vale, Greenwich

Unit 1-4 Garden rooms green roof’s installed. Roof lights to unit 1-4. Portland stone copings completed to units 1-4 rear elevation with green roof installed. 1ST Floor windows installed on front elevation with Portland stone to window reveals.
Read more
The Crane, Hayes

The Crane, Hayes

Currently commencing with 5th lift brick and block work Carpenters starting this week Scaffolders commencing to start birdcages and lifting the perimeter scaffold to get to 3rd floor planks.
Read more
Sunbury Street, Woolwich

Sunbury Street, Woolwich

Drylining close up and ceiling MF to apartments. Block C tape and jointing Blocks A & B lift install Boosted cold water supply pipe work Balcony weathering
Read more
Church Road, Mitcham

Church Road, Mitcham

Building up brickwork to top of padstones Installing final keystone lintels to doorways and windows Preparing site for steel installation
Read more
York Road, Battersea

York Road, Battersea

RC Frame up to seventh floor complete. Columns Level seven to eight formed. Back propping to floors below in place. Ground floor Blockwork to perimeter walls complete. Blockwork progressing in basement.
Read more
The Crane, Hayes

The Crane, Hayes

progressing with 1st lift brick and blockwork in readiness for the 1st floor floor slab to be lift on . All drainage is complete
Read more
Church Road, Mitcham

Church Road, Mitcham

Exterior and interior walls going up to first lift height all around the site. Scaffold following the brick work up to first lift. Steel is in production
Read more
York Road, Battersea

York Road, Battersea

Basement Slab 100% complete Basement liner walls 85% complete. Core walls complete basement to ground floor. Ground floor 50% complete.
Read more
The Crane, Hayes

The Crane, Hayes

installing the attenuation tank and forming the parking area and road. exposing piles and cutting down to the correct level to start forming the ground beams
Read more
How to lay strong foundations for homes built to last

How to lay strong foundations for homes built to last

If you’ve viewed the impressive high rise developments in the Vision Construct property portfolio, you’ll know many of these new builds were completed in and around London. Over the years, we’ve learnt an inordinate amount about laying deep foundations to support heavyweight buildings. We’ve also gained an invaluable understanding of what it takes to lay foundations with minimal disruption to city life. Here’s a little of what we know.

Read more
Going underground - the challenges of a basement dig out

Going underground - the challenges of a basement dig out

Basement dig outs are rarely out of the news in London, as hundreds of homeowners add value to their prime property with a subterranean extension. For Vision Construct meanwhile, basement dig outs tend to be on a larger scale. With space at a premium in vast urban developments of apartments and townhouses, we’re frequently tasked with building underground car parks. Find out how we overcome 2 of the most common excavation challenges

Read more
Why the latest design plans do more for your development

Why the latest design plans do more for your development

Do you have the perfect piece of land to develop but no investment partner? Are you looking for a builder to bring your construction project to life? Or perhaps you need to create a buzz around a new build in progress? Whatever stage you’re at, you’ll find a spectacular set of CAD designs, some detailed floor plans and a range of elevations will hold appeal for potential stakeholders. Read on to find out why.

Read more

Business Hours

Monday - Friday
8:00 am to 5:00 pm
Saturday
Closed
Sunday
Closed