Foxley Lane, Purley

Works have now commenced on our Foxley Lane Purley project to provide 41no. Apartments for Moat Homes Ground Beams, Drainage, Lift Pits and Pad foundations are now complete, works are now focused on installing the Ground floor Slab Vertical Column starters now in place ready for the RC Frame construction Formwork in place for the new RC Core walls and Lift shafts